Fabrication Scheduling
-
Set up the processing priority and create the work packages according to the project requirements:
(such as the material available and required on-site date, on-site installation sequence, etc.); -
Create work package according to different disciplines (piping, structure, electrical & instruments, etc.);
-
Created work package based on different subcontractors (locations, workshops);
-
Each Assembly / Spool can be assigned to a specific team or worker